Im getting the following error and have tried everything to be able to resolve it, can anyone assist please

FundModel=36|ProgType=25|CompStatus=3|LearnStartDate=09/01/2023|AchDate=16/02/2023|



The completion status has not been returned

Replies

No one has replied to this post.


Ben James

You can't have a completion status of 3 and an achievement date. Did the learner complete EPA and fail? Or did they withdraw before completing the EPA? 

(Edited)

Martin West

Snap

This is error CompStatus_07, the completion status should be 2 completed as you have entered the EPA completion date in the AchDate.

HTH

Ben James

As Martin says, it'll either be

Completed all of the EPA on 16/2/23, and passed

  • CompStatus - 2-completed
  • Outcome - 1-achieved
  • AchDate - 16/2/23

Completed all of the EPA on 16/2/23, but failed

  • CompStatus - 2-completed
  • Outcome - 3-no achievement
  • AchDate - 16/2/23

Withdrew before completing all of the EPA

  • CompStatus - 3-withdrawn
  • Outcome - 3-no achievement
  • AchDate - blank

Ashley Roberts

thank you, something so simple easily missed