Hi

Looking for some advice.  

I have an apprentice who started in a previous funding year with the total negotiated price recorded against TNP 1.   Until now there has not been an EPAO assigned.  How do I add the Assessment cost?

Do I need to add a new TNP 1 & TNP 2 to slpit the costs as of the date the EPAO was agreed and would this affect the employers Digital Account in any way.

Replies

No one has replied to this post.


Martin West

Yes but the date must be in the current year for the TNP 1 and 2 that you add, makes no difference to DAS as long as total price the same.