Susan Solomons

LearnDelFAMDateTo_02 Warning

Edited

I've received a warning for a learner on my ILR upload to say.

 'Date applies to' may be wrong. Unless the 'learning actual end date' is later than the 'planned end date', the 'Date applies to' shouldn't be after the planned end date for the learning. Check 'learning planned end date' and 'Date applies to' are correct.

So my learner completed later than originally planned, I'm correct in thinking I don't try to adjust the planned end date just to get rid of the warning do I?  And it's ok to maintain that warning because it reflects what actually happened?

Thanks

Replies

No one has replied to this post.


Martin West

That's correct, a warning is only a warning if its correct you just note the reason (passed planned end date).

Jean Parry

I went on a course where the presenter mentioned this warning message.  You will continue to get this message each month until the end of the academic year when it should clear

Susan Solomons

Thanks Jean Parry, it appears to be a new message because I didn't get it last month.