Hi

I was hoping one of you kind souls could help me with a problem I'm having.

I’ve recorded a break in learning for several apprentices but I’m getting an error which says:

 

CompStatus_07

 

FundModel=36|ProgType=25|CompStatus=6|LearnStartDate=21/09/2020|AchDate=25/06/2021|

 

The completion status has not been returned

 

1ZPROG001

 

I can’t understand this because I have, I think, entered the completion status as: 6 - Learner has temporarily withdrawn from the aim due to an agreed break in learning

Any help would be most appreciated.

Nick

Replies

No one has replied to this post.


Martin West

You do not enter the Achievement Date (ActDate), for a BIL this is the rule description:

For programme aims (LearningDelivery.AimType = 1) that are funded via apprenticeship standards (LearningDelivery.FundModel = 36 and LearningDelivery.ProgType = 25) that ended on or after 1 August 2019 (LearningDelivery.LearnActEndDate => 2019-08-01) and the Achievement date is returned (LearningDelivery.AchDate is known) then the completion status must be 'The learner as completed the learning activities leading to the learning aim' (LearningDelivery.CompStatus = 2)

Nicholas Catterall

Thank you Martin.

Sorry to be a pain but when I remove the achievment date I get this error and I can't understand why:

R122

CompStatus=6|LearnDelFAMType=ACT|LearnDelFAMDateTo=|AchDate=|LearnActEndDate=18/06/2021|

The achievement date is not known, therefore the Date applies to record must be the same as the Learning actual end date.

Martin West

The Date applies to for the latest ACT record must be the same as the Learning Actual End Date and not the achievement date

HTH

Nicholas Catterall

Fantastic! Thank you so much!!