Hi all,
we have a couple of scenarios where apprentices have been restarted after a break in learning but where the component has already been completed and achieved as part of the previous pre BIL record.
As part of the apprenticeship funding rules we should return all open and closed aims until the learner has exited but in this scenario the learner would have already completed and achieved prior to the new restart date so this will error in the ILR.
For example:
C/A in 19/20 on component on 30/04/2020
have restarted with a restart date of the 01/09/2020 in 20/21
If we return the C/A Component aim, this will presumably error as the 30/04/2020 is before the restart date of the 01/09/2020?
0
Replies
No one has replied to this post.
Martin West
You do not include any completed aims when the restart after a BIL, the completed aims will still be shown (returned in the ILR) as you will continue to include the break in learning in your ILR records until either they complete or withdraws.
It is not necessary to include a component aim for a restart after a BIL, but I always advise adding the non-regulated aim if all qualification aims were completed prior to the restart.
Christopher Ashfield
Restart after a BIL where components already achieved
Created
Hi all,
we have a couple of scenarios where apprentices have been restarted after a break in learning but where the component has already been completed and achieved as part of the previous pre BIL record.
As part of the apprenticeship funding rules we should return all open and closed aims until the learner has exited but in this scenario the learner would have already completed and achieved prior to the new restart date so this will error in the ILR.
For example:
C/A in 19/20 on component on 30/04/2020
have restarted with a restart date of the 01/09/2020 in 20/21
If we return the C/A Component aim, this will presumably error as the 30/04/2020 is before the restart date of the 01/09/2020?