Sooty Martin...I have misled you. I am talking about withdrawal dates not completion dates. :) Is it valid to have a withdrawal date of FS that is later than the withdrawal date of the ZProg, based on the evidence of learning activity that is available for both?
Only for functional skills not required for the standard other wise they are part of the Programme so cannot be later than the actual end date of the Programme aim.
Melissa Clark
Learning Aim dates
Created
Hi, what evidence do we use for the last date of learning? We were originally using the Gateway date but now should this be the last day of OTJT?