Claire Ford

Incorrect Start and Expected End dates in 2020/21

Created

None

Good morning. We've just conducted an internal audit on some of our learners and have come across a handful from a single employer who all started a month later than originally planned, and will have their expected end date pushed out by a month. They've been recorded in the ILR has running from Jan21-Jan23 instead of Feb21-Feb23. Can I correct this in the ILR (I know I can correct the expected end date by doing a restart) but is there a way to correct the start date? Or would I be better acknowledging the error in the learner file?

Thanks

Replies

No one has replied to this post.


Martin West

The guidance is: Data entry errors found in ILR data can usually be corrected as soon as the error is found, as long as the error was made in the current teaching year.

You should note the error in the learner file.

HTH

Claire Ford

Thanks Martin