Sally Milner

Learner not attempting EPA

Created

None

We have a learner who is not attempting their EPA but has completed their degree and been awarded. Should both the programme aim and component aim be set to withdrawn and no achievement in this instance?

Replies

No one has replied to this post.


Martin West

The programme aim should be withdrawn but the degree component aim should be recorded as completed and achieved.

HTH

Claire Marshall

Hi,

Sorry for jumping onto this one, we have an apprentice in this scenario also.

I have recorded the degree component aim as completed and achieved and withdrawn the Programme aim.

I am now getting the error 'The achievement date must be 7 days after the learning actual end date' - They haven't sat the EPA, so what date should this be?

Thank you in advance.

Claire

 

Martin West

You do not update the achievement date as they have not completed the EPA.

Claire Marshall

Martin West Should it be the ZPROG that is completed? If so, I am getting an error message of 'The Achievement date must be returned' 

Martin West

No as the on the programme aim the achievement date is when the EPA has been completed.