Hi Christina
Not quite! Per PSM:
You transfer them off the wrong aim *on their original start date* and then add the correct aim with the same start and planned end.
Thank you so much Steve Hewitt I was almost there. I did look at the PSM but could not find the page you sent, thank you.
Christina Marfleet
Incorrect learning aim reference
Created
Morning
I have just discovered a learner who is registered on Diploma in Learning and Development (Early Years Educator) Level 3 Apprenticeship with the awarding body BIIAB but on our MIS system the learner is recorded as being on the EDEXCEL Diploma in Learning and Development (Early Years Educator) Level 3.
It is an admin error and if the learner was a 21_22 start I would just swap the incorrect aim for the the correct one. But the learner started 20_21 so unsure what to do.
In my logic if I end the incorrect aim 01/08/2021 and start the correct aim 02/08/2021 it should be okay but thought I would ask advice here first.
Many thanks
Christina