Martin West commented,
That was an old research document and not policy, the latest from the ESFA is that it is the employers responsibility.
That was an old research document and not policy, the latest from the ESFA is that it is the employers responsibility.
Martin West commented,
No the error indicates the Postcode has not been returned in the ILR and the field is empty (Null)
No the error indicates the Postcode has not been returned in the ILR and the field is empty (Null)
Martin West commented,
You can transfer to a different Standard but this would be a new start.
You can transfer to a different Standard but this would be a new start.
Martin West commented,
Martin West commented,
I think you are correct but the existing skills offer spreadsheet is for the current funding year and may or may not be extended for starts in 21/22 not sure what the policy is for next year.
I think you are correct but the existing skills offer spreadsheet is for the current funding year and may or may not be extended for starts in 21/22 not sure what the policy is for next year.
Martin West commented,
SDL, reports, submission history then download Period end reports
SDL, reports, submission history then download Period end reports
Martin West commented,
Take no notice of the funding approval end date, it is the last date for new starts you need to check.
Take no notice of the funding approval end date, it is the last date for new starts you need to check.
Martin West commented,
No all new starts must meet the minimum duration and the 20% OTJT requirement, for your scenario it is doubtful due to APL that they would be eligible.
No all new starts must meet the minimum duration and the 20% OTJT requirement, for your scenario it is doubtful due to APL that they would be eligible.
Martin West commented,
Individual standards do not have levels as they are related to an occupation. It would have to be a withdrawal and new start.
Individual standards do not have levels as they are related to an occupation.It would have to be a withdrawal and new start.
Martin West commented,
It is a hard lesson to learn but hard close means exactly that and you cannot adjust or alter funding in the previous funding year. You can correct any administrative data errors, see the PSM guidance for correcting errors in a previous funding year but this would not attract or adjust funding.
It is a hard lesson to learn but hard close means exactly that and you cannot adjust or alter funding in the previous funding year.You can correct any administrative data errors, see the PSM guidan...