We use Maytas. You should have a 2021 and a 2022 Leaver ILR. On the 2021 you'll record the status of the apprenticeship and it's aims as they were on 31/07/2022. Then on the 2022 Leaver ILR you'll update the aims (where appropriate) to reflect what the status was from 01/08/2022 onwards.
For instance, if on July 1st the learner completed training, but hadn't done the EPA yet, you'd set the 2021 Leaver ILR to;
2021
- ZPROG completion status - 1 - Continuing
- Learning actual end date - 01/07/2022
- Outcome - 8 - Continuing
- Achievement date - blank
Then, if they completed their EPA and passed in August, you'd update the 2022 Leaver ILR as below, but leave the 2021 Leaver ILR alone;
2022
- ZPROG completion status - 2 - completed
- Learning actual end date - 01/07/2022
- Outcome - 1 - Achieved
- Achievement date - 10/08/2022
When you export your ILRs, you'll need to choose 2021/R13 and 2021/R14 options to ensure you're exporting the 2021 data, and the 2022/R1 and 2022/R2 to ensure you're exporting the 2022 data. Hope this makes sense. But as Martin says, if you're stuck, you can always raise a query with the Tribal service desk.
Laura Howard
R122 rule violation R13 return
Edited
Afternoon all,
I have the following for the same learner but my team are saying all information is present - how do I clear these?
FYI achievement date has been recorded as 18/8/22 - does this have an impact on this?