Hi Oliver,
I've run an R01 this morning and have 83 of these errors, cannot see why, all have been on programme for a while, as you say - ours have various status' and start dates, some original start dates going back to 2021.
Came here to see if anyone has the same before I raise a ticket. I've been through the validation rules (guidance.submit-learner-data.service.gov.uk/26-27/validation-rules/rule/UKPRN_33) and can't see where we have apparently gone wrong.
Hi Alison Hardwick,
We also have 230 R161 errors (If Hours Record 'Planned hours for off the job training due to a reduction in prior learning' (HRS 4) has been returned, 'Price Reduction due to prior learning' (RIP 1) financial record must also be returned).
A handful I believe are genuine because they are still being processed ready to start. Many, however are mid-programme with a start date in 2025/26 and also do not have an "HRS 4" record, not that I can see anyway as there is no new "Hours Record" field in our pre-2026/27 ILRs.
In reply to Rebecca Drury · View original comment
Hi Rebecca,
We also have a number of these errors and I agree with you, some are genuine as they are awaiting RPL Trackers in Aptem which will then populate these fields.
However, as you say, we have a number of errors for learners who have start dates in 25/26!
The other errors I have are
| R30 | All aims that are part of a programme must have a corresponding programme aim with the same Programme type and Standard code |
| R66 | All funded component aims must have a corresponding programme aim with the same Programme type and Standard code |
Again, these learners have 25/26 start dates, the R12 ILR was error free and all have matching data across all aims.
I submitted a ticket this morning so let's see what the response is.
In reply to Helen Bryant · View original comment
Hi Helen,
No response as yet, I'll post here as soon as I hear anything, if anyone else can do the same.
In reply to Alison Hardwick · View original comment
Thanks Alison.
In reply to Lorna Haines · View original comment
Hi Lorna, have you checked your ILR File(s) for a Schema Error at all?
In reply to Rebecca Drury · View original comment
Hi Rebecca, My team have manually added the RIP Price for the 25/26 starts that had R01 error, we haven't added or amended anything to do with hours, and it's got rid of both the RIP Price and HRS errors.
Just submitted and its been removed from errors, also received this from the DFE.
Good afternoon,
Apologies for any inconvenience caused by the UKPRN_33 validation errors.
A defect has been identified with this rule and it has now been temporarily switched off while a fix is being implemented. If you are receiving UKPRN_33 errors, please resubmit your ILR data and validate again.
Thank you for your patience while this issue is resolved.
Response from the DfE...
Good afternoon,
Apologies for any inconvenience caused by the UKPRN_33 validation errors.
A defect has been identified with this rule and it has now been temporarily switched off while a fix is being implemented. If you are receiving UKPRN_33 errors, please resubmit your ILR data and validate again.
Thank you for your patience while this issue is resolved.
Kind regards,
Sumiyyah
Customer Service Support
In reply to Helen Bryant · View original comment
Just re-uploaded and none here Helen
In reply to Alison Hardwick · View original comment
Ok, thanks Alison. Maybe I'll re-upload again and see what happens.

Oliver Green
UKPRN_33 Error in R01 Submission
Created
We have run our first 26/27 R01 submission this morning, and there appears to be 25 errors with the UKPRN_33 error code. Is anyone aware of any known issues within the 26/27 R01 submissions? If not, does anyone have any advice on how to resolve the errors. All of the learners seem to have started in the last couple of contract years, and on checking, all of the UKPRN's are correct across the ILR and App Service. Thanks