Gill Knight created a post,

QAR - Withdrawal and then restart

We have a learner that left in early 2025/6 whose planned end date was in 2026/7 which means their hybrid year would be 2026/7. This month it has been agreed that they can return to the standard to...

Community Reply

Gill Knight created a post,

PDSAT

Has anyone run PDSAT today?  some of the outputs in the file are gobbledygook There is a new column called Apprenticeship standard version and then I have funding adjustments showing as 4518000%  a...

Community Reply

Gill Knight created a post,

Withdrawal within 42 days, now wants to restart