Thao Nguyen created a post,

ILR picks up old funding band

We have a learner who was initially registered for a Level 3 apprenticeship in 2022. They were then withdrawn with end date the same as start date as they changed to the Level 2. The learner has si...

Commmunity Post

Thao Nguyen created a post,

Employer change whilst on break - DAS

We have 2 apprentices who changed employers during their break (or more so change to a different DAS account). I have told the employer that we will action this when the learners are back in learni...

Commmunity Post

Thao Nguyen created a post,

6 week leavers counted towards QAR

We have a few 6 week leavers that have been counted towards our QAR. We have disputed a few. However, for the other ones, I am not sure if they are classed as 6 week leavers, because they were put ...

Commmunity Post

Thao Nguyen commented,

Also, If I am looking at this document here, the Hyb...

Also, If I am looking at this document here, the Hybrid year end is either: • the achievement year of an apprenticeship• the actual end year of an apprenticeship• the planned end year of an apprent...

Commmunity Post

Thao Nguyen commented,

Some of our programmes have very long EPA process, s...

Some of our programmes have very long EPA process, so their EPA period can last 6 months. So learning planned end is when they are supposed to complete all their learning and ready for gateway and,...

Commmunity Post

Thao Nguyen commented,

Sorry, should have given all the details, shouldn't ...

Sorry, should have given all the details, shouldn't I. Start date: 14/04/2022 Learning expected end: 13/05/2023 Expected end: 13/01/2024 Actual end: 31/03/2023 Achievement date: 11/05/2023 Date pr...

Commmunity Post

Thao Nguyen commented,

Thanks Ben. So an example: Start date: 14/04/2022 ...

Thanks Ben. So an example: Start date: 14/04/2022 Learning expected end: 13/05/2023 Expected end: 13/01/2024 Actual end: 31/03/2023 Can I confirm what it means by reporting year? We report monthl...

Commmunity Post

Thao Nguyen created a post,

Hybrid year confusion

I understand that the hybrid end year is the later of the:  achievement year (for apprenticeship standards on funding model 36 only)  planned end year of the learning aim actual end year of the le...